Albany, GA – The SPLOST VII alley paving list for 2020 was presented to the Board of Commissioners by the City Engineering Director Bruce Maples. The list includes alleys in all wards throughout the City.

On April 23, 2019, the Commission approved a list of alleys for repaving to be funded by SPLOST. Subsequently, the engineering and design was completed along with identification of numerous easements that would be required.

The project consists of asphalt pavement installation on approximately 2.5 miles of City unpaved alleys. Work includes demolition, clearing, erosion and sedimentation measures, grading, storm drainage, sewer/water/gas relocation, concrete driveways and pavement and curbing, soil cement base, prime coat, and 2” asphalt surface course, and all associated work as required. Jim Boyd Construction, Inc. was the lowest responsive and responsible bidder. The project will cost approximately $1,759,559.55. The contract time is three hundred and sixty (360) calendar days.

This item will be placed on the July 28 Regular Agenda for a decision.